Oro General Hospital renovation is 85% completed - Project Manager

 Oro General Hospital renovation is 85% completed - Project Manager


By:  Olayioye Olaide Solomon



The Project Manager, Oro General Hospital in Irepodun Local Government Area of Kwara State, Architect Theophilus Kusimo said the renovation of the hospital is at 85% completion and will soon be delivered to the state governmen. 


The Project Manager in an interview, disclosed that their delivery is very close and their time schedule now is to ensure that the wards and the main operating system of the hospital is in place first to move doctors to their permanent offices. 


“We will then do the theatre last to avoid any infection into the place. All we have left now is the theatre and administrative block," the project manager Architect Theophilus Kusimo told reporters during a visit to the site”


Kusimo commended the Oro community for their accommodation and support, saying his team is enjoying extreme support from the people of Oro Kingdom.


"We are enjoying the support of the host community. They are very happy with the project. They come here weekly to do their own assessment and they are extremely very happy, knowing fully that we are doing the best for them, we are not cutting corners. They come for inspection with their experts too. Over 95% of our workers are actually from this axis," Kusimo added.

Comments

Popular posts from this blog

Tunisia defeats Nigeria As Super Eagles Crash Out Of 2021 AFCON

Lack of waste bin cause water pollution in Sahoo, residents decried. By: Muhammad Sanni Aisha

KWASU LUNCH 40 NEW SHUTTLE BUSES